Hello all,
With Remedy ARS 4.5 and Change Management 4.0.3, if the "Approval Process" for a particular Change Request has already restarted, and it needs to be 'reset', Remedy's reccommendation is to move the current Change Request's 'Approval Status' to "Approval Process Canceled" and to open a new Change Request. My org was not content with this, so I have been walking down the road of how to in effect reset the approval process while remaining on the same Change Request. I have nearly completed my specs and workflow discovery for this enhancement, but just wanted to ask if anyone else has attempted / accomplished this, and if so do you mind sharing your basic approach?
Thanks,
Kenny Young
(501)905.4438
Sr. C/S Developer
ACI Remedy IT Support
ALLTEL